800 V DC at the generator
Isolation and AC-to-DC conversion happen inside the generator. No transformers, switchgear or separate rectifiers between the turbine and the racks.
Hyper Tech · Data-centre power
Hyper Tech is developing natural-gas turbine-generator packages, built from existing CFM56 aero engines, designed to deliver 800 V DC directly from the generator to the racks, with no transformers, switchgear or separate rectifiers in between.
The problem
US data centres could use 11.8 % of the country's electricity by 2030 (range 9.5–15.3 %).
New gas-turbine slots are largely committed to 2029–2030, and transformers take 2.5–4 years at current lead times.
A 1 MW rack draws 18,500 A at 54 V but 1,250 A at 800 V DC. The latest GPU and CPU architectures are moving to 800 V DC.
The solution
A conventional turbine plant makes AC and reaches 800 V DC through transformers, switchgear and separate rectification. In CROSSOVER the generator converts 600 V AC to 800 V DC itself and feeds the racks on the shortest possible DC buses.
No longer required with CROSSOVER
Why CROSSOVER
Isolation and AC-to-DC conversion happen inside the generator. No transformers, switchgear or separate rectifiers between the turbine and the racks.
Built from existing aero engines, outside the queue for new turbines and the transformer backlog. First unit and pilot targeted for Q2 2028.
About $1,590 per kW against about $2,450 to reach 800 V DC conventionally: about 35 % less equipment cost, and about $83 per MWh against $100 for an AC turbine with DC conversion (modelled).
Multiple isolated buses of 2–5 MW, each with local fuses and IGBT controls. Fewer components, no gearbox, a smaller footprint.
The numbers
CROSSOVER burns the same natural gas as any simple-cycle turbine, about $43–45 per MWh at 37–39 % efficiency. It costs less at the racks because an AC plant also pays for transformers, switchgear and rectifiers, and loses 3–5 % in them.

A conventional 25 MW plant needs about $2,450 per kW of equipment to deliver 800 V DC: the turbine-generator, then transformers, switchgear and breakers, then AC-to-DC conversion. CROSSOVER is about $1,590 per kW, because the conversion chain is inside the generator.
~$860 per kW saved, about $0.86B per GW (modelled)
| Option, $ per MWh at the racks (800 V DC) | Natural gas | Generator capital | DC conversion | O&M | Total | Availability |
|---|---|---|---|---|---|---|
| Hyper Tech CROSSOVER, 800 V DC direct | 45 | 26 | – | 12 | 83 | First unit Q2 2028 (target) |
| Simple-cycle turbine, AC + DC conversion | 45 | 28 | 15 | 12 | 100 | Slots largely committed to 2029–2030 |
| Natural-gas combustion engines (reciprocating), AC + DC conversion | 38 | 32 | 15 | 12 | 97 | Typically 12–18 months for large orders |
| Combined cycle, AC + DC conversion | 30 | 31 | 15 | 6 | 82 | 4–6 years to build, 100 MW+ |
Modelled. One basis for every row: natural gas at $4.40/MMBtu (HHV), 85 % load factor, 15 years at a 9 % cost of capital. AC plants add $850/kW of transformers, switchgear and rectifiers and lose 4 % on the way to 800 V DC. CROSSOVER: 37.1 % efficiency (16 MW), $1,590/kW. Simple-cycle turbine: 38.5 %, $1,600/kW, same maintenance allowance. Natural-gas combustion engines: EIA heat rate and O&M, $1,850/kW. Combined cycle: Lazard LCOE+ 2026 midpoints. Diesel sets burn about $400 of fuel per MWh at $6 a gallon, so they are for backup. Estimates, not quotes.
Want this model run for your site? Request the NDA
What it looks like
The generators sit on the engine shaft and rectify on the machine. The DC leaves the skid on a short connection to the GPU modules. Select a picture to enlarge it.
The business opportunity
Data centres need tens of gigawatts of on-site power this decade, the racks are moving to 800 V DC, and the engines to build from are retiring every year.
A ~40 GW on-site power gap for data centres, 2026–30, at ~$2,450/kW for conventional plant to reach 800 V DC.
CFM56 engines in service worldwide, the most-built jet engine family.
Engines a year expected to retire, as retirements rise from about 2 % to 3–4 % of the fleet between 2026 and 2027.
The latest GPU and CPU architectures are moving to 800 V DC. CROSSOVER is designed to deliver it from the generator.
The same 800 V DC buses can later take fuel cells from Global Research & Development, Hyper Tech's companion company. What comes next
Investing in power for AI? Request the investor NDA
Programme and milestones
CROSSOVER is a development programme. Design and manufacturing are in the United States, close to the customer. Dates are design targets.
Isolated multi-phase windings in one machine; MVA-class conversion to DC.
The generator package tested under load.
First-of-a-kind unit at a data-centre pilot site.
16 MW units, with a pathway to 20 MW.
Planning capacity for 2028 and beyond? Talk to us about the pilot
What comes next
Global Research & Development Inc., Hyper Tech's companion company, is developing nano-membrane solid oxide fuel cells that produce DC directly and are packaged as 800 V DC units of 1 MW and up. A campus built on Hyper Tech's isolated DC buses can add or switch to them without rebuilding its power distribution.
Scale-up path: from single tube cells to a multi-tube module, then a stack on Hyper Tech's 800 V DC test stand (2027) and a 1 MW unit on one bus at the data-centre pilot (2028).
Fuel cells are already bought at data-centre scale: Oracle has agreed up to 2.8 GW of solid oxide fuel cells from Bloom Energy, with 1.2 GW firm (April 2026).
Natural-gas turbine-generator packages for behind-the-meter power: 16 MW per unit, with a pathway to 20 MW.
Electrical efficiency target. The cells are multi-fuel: hydrogen, methane or natural gas, propane, and JP-8. At $4.40 gas that is a fuel cost of about $28/MWh, against about $43–45 for the turbine.
Than present-day fuel cells, with a $2,000/kW target at scale. The electrolyte stack is under 800 nm thick. The same platform offers options for PFAS removal and on-site oxygen production.
Fuel-cell figures are Global Research & Development targets, not test results. Fuel cost computed here from the 60 % target at $4.40/MMBtu (HHV), assuming 98 % DC/DC to the bus. Liquid fuels such as JP-8 need sulfur removal and pre-reforming ahead of the stack. Oracle–Bloom figures as reported by enkiai.com (April 2026).
Brochure
The four-page brochure covers the two power chains, where the equipment cost goes, how CROSSOVER compares with other on-site options, and the cost of electricity at the racks. Select a page to read it.
Who it is for
The public pages show the concept. The design data, the site economics and the financial model are shared under a mutual NDA.
Hyperscalers and data-centre developers
Under NDA: generator design and test data, site interface and footprint, the cost-of-electricity model run for your site, and the pilot programme.
Request the NDA as a data centreInvestors
Under NDA: the investor document, financial model, use of proceeds, terms, and the data room with the cycle model and generator design.
Request the NDA as an investorEngine supplier, manufacturer or EPC partner? Request the NDA as a partner.
Next step
Tell us who you are. We send a mutual NDA, then arrange a briefing and access to the data room.
Or contact Michael Tomsic, President, directly
mtomsic@hypertechresearch.com +1 740-517-3569Hyper Tech Research, Inc., 539 Industrial Mile Rd., Columbus, Ohio